Thursday, November 29, 2012

More Happening Than You Think

While we wait for the delivery of our elevator coach, work continues on some final details.
 

There will be a call button next to the lobby entrance. For now, it makes a great cat toy.

A view of the outside entrance to the elevator lobby.

This is the mechanical room which will house the elevator equipment when it arrives. The location was created out of former office space in the basement of the Albright.

Saturday, November 24, 2012

Project Delayed Due to Elevator Delivery


The November 22nd issue of The Scranton Times-Tribune contained an article on project delays due to the delivery of the elevator coach. In the meantime, work continues. In the photo below you can clearly see a small lobby, newly constructed, where elevator riders will be able to wait for a coach without having to suffer the elements.


Thursday, November 15, 2012

Facade Almost Complete

You can see from this photo that the installation of the facade for the elevator enclosure is almost complete. Every effort has been taken to make it match, as closely as possible after almost 120 years, the original stone used in the construction of the Albright.

Friday, November 2, 2012

The Forbidding Door

The photos below were taken during the day so why does it appear to be midnight outside? Solar eclipse? Some kind of terrible cataclysm? Well, no. Darkness is simply proof that the elevator enclosure has been completed. We are now waiting for the application of the facade and the delivery of the elevator itself. In a matter of weeks, this door, formerly the rear handicapped entrance, will be replaced by an elevator stop.




Proof that it is truly daytime. The outside elevator entranceway provides a glimpse of the contruction site.